GTU · IE 402 Project Development & Management · Fall 2026 · Dr. Suat Genç

Midterm guide

All five lectures explained, the points the professor flagged for the exam, and written practice questions in the exam's format: explain, draw, list. Lara ⭐

Lecture 1Introduction to project management

Why we care: delivering value

For-profit and non-profit organizations both exist to deliver value to customers or stakeholders, who in return keep them alive. Porter's value chain shows how a firm creates that value:

  • Support activities: firm infrastructure, human resource management, technology, procurement.
  • Primary activities: inbound logistics → operations → outbound logistics → marketing & sales → service.
  • What is left after all costs is the margin. Projects are one of the main ways an organization creates new value.

Permanent work vs temporary work

Permanent work (operation)Temporary work (project)
Lecture exampleMaking chocolate: cocoa pods → beans → fermentation → drying → roasting → shelling → grinding → sterilization → mill → conching → chocolateDeveloping a new chocolate: experimenting with kadayıf, pistachio paste, tahini, coconut oil, white chocolate → Dubai chocolate
DurationRepeats every dayHas a start and an end
OutputThe same productA unique new product

What is a project?

A project is a “temporary endeavor” to create value through unique products, services and processes. Projects have a team, a budget, a schedule and a set of expectations the team must meet. Tasks are carried out as work over a period of time and lead to a unique result.

The project triangle (triple constraint). Time, cost (money and people) and scope are linked; quality sits in the middle. Changing one side forces a change in another.

Project development and project management

The course covers both. They use different methods and answer different questions.

Project developmentProject management
Used forDeveloping a project idea, prototyping it and testing its performance or quality with customersImplementing the project, considering resources, time scale, budget and all business and commercial issues
MethodDesign Thinking: Empathize → Define → Ideate → Prototype → TestPM life cycle: Initiation → Planning → Execution → Monitoring & Control → Closure
QuestionWhat and why?How and when?
RoleResearches, plans and completes the project; involved from the very start; ensures compliance with local, national and international regulations; raises financing from investorsOversees day-to-day operation; manages workforce, budget and timeline; works closely with the developer; solves problems with crew, materials or equipment; monitors deadlines, safety and workmanship

Examples of big projects

  • Türkiye: Istanbul New Airport, Kanal Istanbul, the domestic electric car (TOGG), e-Devlet, Eurasia Tunnel, Antalya Expo Centre.
  • BMC Power 1500 hp power pack: 400 engineers, 600 global suppliers, 3,000 parts designed from scratch; first phase 2019–2023. It survived strategic expectations, military embargoes, pandemic lockdowns and technical difficulties, which the professor uses as an example of good project management.

Project management as a profession

Project management is centuries old (pyramids, Great Wall, Taj Mahal). After the mid-20th century it became a formal discipline with guides and tools: Gantt chart, CPM, PERT, WBS, risk management, Waterfall, Agile.

YearMilestone
2570 BCGreat Pyramid of Giza completed
208 BCGreat Wall of China
1917 ★Henry Gantt: the Gantt chart
1931Hoover Dam project
1956American Association of Cost Engineers (AACE) formed
1957 ★Critical Path Method (CPM), DuPont
1958 ★PERT, US Navy Polaris project
1962 ★US Department of Defense mandates the WBS
1965 ★IPMA founded
1969 ★PMI launched
1975 ★PROMPTII (Simpact Systems); Brooks, The Mythical Man-Month
1984Theory of Constraints (Goldratt, The Goal)
1986Scrum named as a management style
1987 ★PMBOK Guide published by PMI
1989 ★PRINCE developed from PROMPTII; Earned Value Management elevated
1994First CHAOS report on project failures
1996 ★PRINCE2 released (CCTA)
1997 ★Critical Chain Project Management (CCPM)
1998 ★PMBOK becomes an ANSI standard
2001Agile Manifesto
2006 / 2008 / 2009AACE Total Cost Management; PMBOK 4th ed.; PRINCE2 major revision
2012 ★ISO 21500:2012 guidance on project management; PMBOK 5th ed.

★ = marked with a red dot by the professor. Two schools came out of this history: PMI (USA: PMI → PMBOK → ANSI → ISO 21500, certificate PMP) and PRINCE (UK: PROMPTII → PRINCE → PRINCE2, certificate PRINCE2 Practitioner).

Phases in the two approaches

  • PMI: Initiating → Planning → Executing → Monitoring & Controlling → Closing.
  • PRINCE2: Starting up a project → Directing a project → Initiating a project → Controlling a stage → Managing product delivery → Managing stage boundaries → Closing a project.

Key elements of a project

  • Unique product (a component), service (a call centre) or result (research findings).
  • Temporary endeavor: a defined beginning and end; short (new product architecture) or long (an airport).
  • Drives change: moves the organization from a current state to a future state through project activities.
  • Creates value: tangible and intangible benefits such as money, market share and brand recognition.

Why projects are initiated (initiation context)

  1. Meet regulatory, legal or social requirements
  2. Satisfy stakeholder requests or needs
  3. Create, improve or fix products, processes or services
  4. Implement or change business or technological strategies

Good vs poor project management

Good PMPoor PM
Meets business objectives and stakeholder expectations; more predictable; higher chance of success; right product at the right time; resolves problems; responds to risks in time; optimal use of resources; identifies, recovers or terminates failing projects; manages constraints; balances trade-offs; manages change betterMissed deadlines, cost overruns, poor quality, rework, uncontrolled expansion of the project (scope creep), loss of reputation, unsatisfied stakeholders, failure to achieve objectives

Portfolio, program, project

  • Portfolio: a group of programs and projects put together to meet the strategic objectives of the business.
  • Program: a group of related projects.
  • Project: a temporary endeavor to create a unique result.
Organizational strategy→Portfolio→Programs→Projects / operations→Shared resources & stakeholders

OPM (Organizational Project Management) is the framework that integrates portfolio, program and project management with organizational enablers to achieve strategic objectives: strategy → portfolio (value decisions) → programs and projects (deliver results) → operations (business value realized), with feedback back to strategy.

Project components

  • Project life cycle: the series of phases from start to completion (starting, organizing & preparing, carrying out the work, ending).
  • Phase: related activities that end in a deliverable (idea, design, prototype).
  • Phase gate: a review at the end of a phase where a decision is made to continue, change or stop.
  • Process groups: logical groupings of inputs, tools and outputs (initiating, planning, executing, monitoring & controlling, closing).
  • PM processes: systematic activities that turn inputs into outputs (collect requirements, identify stakeholders, schedule activities).
  • Knowledge areas: the 10 PMBOK areas (Lecture 3).

Organization types

Projects can sit in a functional organization (team reports to functional managers), a project-oriented / projectized one (team reports to project managers) or a matrix (team members report to both).

From functional to projectized, the project manager's authority and access to resources rise.
FunctionalWeak matrixBalanced matrixStrong matrixProjectized
PM authorityLittle or noneLowLow–moderateModerate–highHigh–almost total
Resource availabilityLittle or noneLowLow–moderateModerate–highHigh–almost total
Who manages the budgetFunctional managerFunctional managerMixedProject managerProject manager
PM rolePart-timePart-timeFull-timeFull-timeFull-time
PM admin staffPart-timePart-timePart-timeFull-timeFull-time

The project manager

Spheres of influence: the project (lead the team to objectives), the organization (work well with other PMs), the industry (follow trends), professional discipline (keep learning, transfer knowledge) and across disciplines (explain the value of PM to other professionals).

PMI Talent Triangle: technical project management · leadership · strategic and business management.

Management (direct from A to B with known behaviours)Leadership (guide from A to B through discussion)
Uses positional power; maintains; administers; focuses on systems and structure; relies on control; short-term goals; asks how and when; focuses on the bottom line; accepts the status quo; does things right; operational issues and problem solvingUses relational power; develops; innovates; focuses on relationships; inspires trust; long-term vision; asks what and why; focuses on the horizon; challenges the status quo; does the right things; vision, alignment, motivation, inspiration

Both are needed. In the course framework, the actual engineering and technology work (ask → imagine → design → improve) happens inside the Executing phase; project management is the frame around it.

Lecture 2Project types, methodologies, project charter

Two points from the framework drive this lecture: the high-level decision and approval before Initiation (business case, charter) and the engineering and technology development work inside Execution (development methodologies).

Project types

TÜBİTAK runs many project types: method, technology, model, facility, software, product, process, system and platform development; proposal preparation; feasibility and characterization studies; data analysis; training; consultancy; certification; pre-production; field service; standard development. The lecture focuses on technology development and product development.

Project portfolio monitoring map

Projects are placed on two axes: value presented (pre-analysis → technology development → product → process → system/facility → production → facility monitoring/inspection → field service → training/consultancy) and resources used (know-how → personnel → equipment → reliability/brand name → independent authority → location → legal requirements).

  • Good (green): value comes from know-how and people, e.g. technology development.
  • Bad (red): value comes only from legal authority, location or independent-authority status, e.g. inspection work.
  • The improvement direction is toward knowledge-intensive, high value-added projects.

Development methodologies

Each field (construction, facility, technology, software, process and service, product) has its own methodology. Every stage ends with a milestone where the team stops, reviews and evaluates performance before continuing (a phase gate).

TypeStages and stepsStarts from
Technology developmentC Concept: C1 functional structure, C2 concept development, C3 functional model, C4 proof of concept, C5 critical parameters, C6 robust model → M1
F Feasibility: F1 subsystem test setup, F2 testing & optimization, F3 system test setup, F4 tolerance design planning → M2
R Readiness: R1 tolerance optimization, R2 system test setup preparation, R3 verification tests → M3
A physical working principle
Product development (e-scooter)C Concept: C1 voice of customer & specifications, C2 concept generation & selection, C3 subsystem specifications → M1
D Design: D1 subsystem design, D2 part design → M2
R Readiness: R1 system verification, R2 preparation, R3 pilot production → M3
Voice of the customer
Service development (gym)P Planning: business strategy, new service strategy, idea generation, concept development & evaluation, business analysis → M1
I Implementation: service development & testing, market testing, commercialization, post-launch review → M2
Business strategy
Construction (house)10 milestones: site & foundation, rough framing, siding/roofing/rough plumbing-electrical-HVAC, insulation, drywall & interior fixtures, trim & exterior walkways, hard flooring & grading, mechanical trim & bathroom fixtures, mirrors & landscaping, final walk-throughThe site

Technology vs product

Technology is the use, application or knowledge of physical or chemical principles or methods to perform a certain function. A product is an object that uses a technology to ideally meet market needs or wants (high quality, low cost…).

A function is written as verb + noun: measure flow, heat the room, sense speed.

One function can be done by several technologies; one technology can be used in several products.
Flowmeter technologyWorking principleEnergy chain
Tapered tubeKinetic energy of the fluid becomes pressure, pressure becomes force; the float rises and is read by eye (Bernoulli: ρv²/2 + ρgh + p = constant)½mV² → PA → F
Hot wireA heated wire is cooled by the flow; the heat loss is measured as electrical powerAh(ΔT) = V·I = W
Paddle wheelThe flow turns a wheel; a dynamo produces electricity½mv² = ½Iω² = V·I = W

Example function “heat the room”: if you use an existing technology, you are doing product development; if you build a new working principle from physical equations, you are doing technology development.

Technology development: the concept steps

  1. C1 Functional structure: break the primary useful function into sub-functions (sense speed, determine flow, display flow).
  2. C2 Concept development: generate alternative solution concepts for each sub-function (float, hot wire, paddle wheel) and select.
  3. C3 Functional model: connect all functions with flows of energy, material and signal (inputs: kinetic energy, liquid; outputs: data on display, electrical energy, liquid).
  4. C4 Proof of concept: write the physics behind each function (½mv², Bernoulli, ½Iω², Faraday ε = −dΦ/dt). Conservation of energy and mass must be proven: mass in = mass out, energy in = energy out.

Project pre-work: getting approval

Needs assessment→Business case↔Benefits management plan→Project charter→Project management plan

Professor's note: “You need approval first, then you can continue. What is the benefit for me, for the company and for the customer? What is the net profit?”

Telling the business case

Dimensions: customers, problem, solution, competitors, value proposition (why would the customer buy it, what are its advantages), business model, future work.

FormToolNotes
OralElevator pitch, 2 minutesCatch the listener; practise to finish on time. A technical pitch covers how it works (needs and functions), core competence, key partnerships, value created and delivery, key technical success measures.
WrittenBusiness plan, 6–10 pages (NABC)“Not an easy way.”
DemoMVP (minimum viable product)A simulation of the product, e.g. the pupwalk dog-walking app screens.

NABC

A business case lists objectives, required investment and financial and qualitative success criteria. It is used to make the go / no-go decision.

QuestionNetflix vs Blockbuster example
NeedWhat is the customer and market need?Movie rental is a €500M business; people dislike poor service, returning cassettes and late fees
ApproachWhat is your unique approach?Video on demand over existing channels and hardware; no new investment for users, same price
BenefitsWhat are the tangible benefits for stakeholders?No returns, no late fees, DVD-like functions; higher revenue and margin per film, 20% market share expected
CompetitionWhy are the benefits superior to competitors? (USP)Online rental has higher handling costs; mailing back is as much trouble as going to the store

Stakeholders and the charter

Benefits management plan: regularly identify project stakeholders and analyse and document their interests, involvement, interdependencies, influence and potential impact on project success. Internal: employees, managers, owners. External: suppliers, society, government, creditors, shareholders, customers. Professor: “Anyone who affects our business can be a stakeholder” (BMC example: Land Forces, ministries, suppliers, local governments, political parties).

The project charter formally authorizes the existence of a project and gives the project manager the authority to apply organizational resources. Sections: project name, PM and sponsor, start/end dates, business need, scope, deliverables, risks and issues, assumptions and dependencies, financials (budget), milestones, project team, approval/review committee.

Lecture 3Integration, scope and schedule

This lecture is about Planning.

Risk is highest at the start and declines over the life cycle; the cost of changes (and staffing) is low at the start and rises as work progresses.
Process groups overlap in time. Executing takes the most effort; monitoring and controlling runs through the whole project.

Process groups × knowledge areas

Knowledge areaInitiatingPlanningExecutingMonitoring & ControllingClosing
1 Integration1.1 Develop project charter1.2 Develop PM plan1.3 Direct & manage work; 1.4 Manage knowledge1.5 Monitor & control work; 1.6 Integrated change control1.7 Close project or phase
2 Scope2.1 Plan scope mgmt; 2.2 Collect requirements; 2.3 Define scope; 2.4 Create WBS2.5 Validate scope; 2.6 Control scope
3 Schedule3.1 Plan schedule mgmt; 3.2 Define activities; 3.3 Sequence activities; 3.4 Estimate durations; 3.5 Develop schedule3.6 Control schedule
4 Cost4.1 Plan cost mgmt; 4.2 Estimate costs; 4.3 Determine budget4.4 Control costs
5 Quality5.1 Plan quality mgmt5.2 Manage quality5.3 Control quality
6 Resource6.1 Plan resource mgmt; 6.2 Estimate activity resources6.3 Acquire resources; 6.4 Develop team; 6.5 Manage team6.6 Control resources
7 Communications7.1 Plan communications mgmt7.2 Manage communications7.3 Monitor communications
8 Risk8.1 Plan risk mgmt; 8.2 Identify risks; 8.3 Qualitative analysis; 8.4 Quantitative analysis; 8.5 Plan responses8.6 Implement responses8.7 Monitor risks
9 Procurement9.1 Plan procurement mgmt9.2 Conduct procurements9.3 Control procurements
10 Stakeholder10.1 Identify stakeholders10.2 Plan engagement10.3 Manage engagement10.4 Monitor engagement
Patterns: Initiating has only two processes (charter, identify stakeholders); Closing has only one (close project or phase); Planning has the most. Scope, Schedule and Cost have nothing in Executing. All planning processes feed one document: the project management plan.

Integration management

Integration covers the processes to identify, define, combine, unify and coordinate the processes of all other areas: resource allocation, balancing competing demands, examining alternatives, tailoring processes to objectives, managing interdependencies.

The project management plan describes how the project will be executed, monitored, controlled and closed. It integrates all subsidiary plans and the baselines, and states the approvals, conflict resolution and control against the scope, schedule and cost baselines. Professor's note: it is an expanded, more detailed version of the charter.

  • Plan components (18): scope, requirements, schedule, cost, quality, resource, communications, risk, procurement, stakeholder engagement, change and configuration management plans; scope, schedule, cost and performance measurement baselines; life cycle description; development approach.
  • Project documents (33): records produced during the work, e.g. activity list, assumption log, issue log, lessons learned, milestone list, requirements traceability matrix, risk register, stakeholder register, quality reports.

Scope management

Professor: “What will you develop? What will be achieved?” Product scope = the features and functions of the product. Project scope = the work performed to deliver it; the boundaries of the project, the expectations given in the contract.

  1. Plan scope management: document how scope will be defined, validated and controlled.
  2. Collect requirements: determine, document and manage stakeholder needs.
  3. Define scope: a detailed description of the project and product.
  4. Create WBS: subdivide deliverables and work into smaller, manageable components.
  5. Validate scope: formal acceptance of completed deliverables.
  6. Control scope: monitor scope status and manage changes to the scope baseline.

Collecting requirements

  • Tools: brainstorming, interviews, focus groups, questionnaires, benchmarking, document analysis, voting, multicriteria decision analysis, affinity diagrams, mind maps, nominal group technique, observation, facilitation, context diagrams, prototypes.
  • Outputs: requirements documentation and the requirements traceability matrix (RTM), which tracks each requirement through design, development, test and deployment so none is forgotten.
  • Requirement levels: business (sponsor's view, scope, business goals) → user (user's goals, inputs and outputs) → system (functional and non-functional).
  • Sources: customer domain (marketing literature, agreements), company domain (policies, business rules, plans, processes, problem reports, field data), government domain (laws, regulations, standards).

Business strategy decides the requirements

Scope \ advantageCostDifferentiation
Broad marketCost leadership: lowest-cost producer (economies of scale, proprietary technology, raw materials)Differentiation: unique on attributes buyers value, rewarded with a premium price
Narrow marketCost focusDifferentiation focus
  • Choose the segment level (BMW Z4 → BMW → luxury car → car → land vehicle → transportation); the competitors change with the level.
  • User types: lead user, satisfied, dissatisfied, former customer, never bought. Buyer types: system integrator, distributor, retailer, customer.
  • For low-cost ideas, talk to people who know your product. For differentiation ideas, talk to people who are not your customers.
  • Interviews capture needs in the customer's own words (two interviewers, or one with a recorder). Contextual inquiry observes needs in behaviour; location, people, culture and values matter.

Defining scope

The scope statement lists deliverables, acceptance criteria and exclusions. Requirement categories: performance, functionality, ergonomics, aesthetics (the five senses), cost, service and maintenance (accessibility, time and cost to service), health and safety, standards, sustainability. Writing the exclusions prevents disputes and scope creep.

Work Breakdown Structure

Create WBS = subdivide project deliverables and work into smaller, more manageable components. Inputs: scope management plan, scope statement, requirements documentation. Tools: expert judgment, decomposition. Output: the scope baseline. Requirement IDs (1.0 → 1.1, 1.2…) become branches; the lowest level is the work package.

A three-level WBS. Durations and costs are estimated at the work-package level.

Professor: “Check your WBS against customer expectations and requirements. Develop it from the customer requirements.”

Schedule management

The schedule is the detailed plan of how and when the project will deliver the scope; it is the basis for communication, managing expectations and reporting.

  1. Plan schedule management
  2. Define activities
  3. Sequence activities
  4. Estimate activity durations
  5. Develop schedule
  6. Control schedule

Sequencing: the precedence diagramming method (PDM)

Every activity except the first and last must have at least one predecessor and one successor. Example: build the wall (predecessor) → paint the wall → install curtains (successor). Professor's note: we need to minimize the duration.

The four logical relationships. FS is the most common, SF the rarest.
RelationRuleSlide exampleProfessor's example
FS finish-to-startSuccessor cannot start until predecessor finishesInstall OS after PC hardware is assembledBuild wall → paint wall
FF finish-to-finishSuccessor cannot finish until predecessor finishesEditing finishes after writing finishesLights off after the lecture ends
SS start-to-startSuccessor cannot start until predecessor startsLevel concrete after pouring startsWork starts after insurance starts
SF start-to-finishSuccessor cannot finish until predecessor startsOld accounting system shuts down after new one startsRemove oxygen mask after breathing starts

Lead = how much a successor can be advanced (written minus: FS − 2 weeks, landscaping before the punch list ends). Lag = how much a successor is delayed (written plus: SS + 15 days, editing after writing starts). The schedule network diagram shows activities, relationships, leads and lags.

Estimating durations: three-point estimate

Most likely tM (realistic expectations), optimistic tO (best case), pessimistic tP (worst case). Numbers come from expert judgment.

tE = (tO + tM + tP) / 3   e.g. (4 + 6 + 14) / 3 = 8 days

Developing the schedule: critical path method

CPM estimates the minimum project duration and the scheduling flexibility (float) on each path. A forward pass gives early dates, a backward pass gives late dates.

  • Forward: ES = largest EF of predecessors; EF = ES + duration.
  • Backward: LF = smallest LS of successors; LS = LF − duration.
  • Float = LS − ES = LF − EF. The critical path is the chain with zero float, the longest path; any delay on it delays the project.
Lecture example. Critical path A → C → F → H = 3 + 6 + 4 + 8 = 21 days.
ActivityDur.ESEFLSLFFloat
A303030
B437592
C639390
D67139152
E47119132
F49139130
G6131915212
H8132113210

Professor's notes: “We consider the critical path.” For an activity with float (E has 2 days) you can use a slower machine or fewer people to reduce cost or improve quality.

Resource leveling vs smoothing

Resource levelingResource smoothing
Adjusts dates toBalance demand with resource supply (e.g. Sue cannot work 16 h on day 1)Keep resource use within predefined limits
Critical pathCan change; project may get longer (Sue: 2 days → 3 days)Does not change; activities move only within their float

Schedule compression

Fast tracking runs phases in parallel (higher risk and rework). Crashing adds overtime, people or money (higher cost).

Schedule levels: milestone schedule (zero-duration points) → summary schedule (work packages) → detailed schedule (activities and relationships), usually shown as a Gantt chart whose colours match the WBS.

Lecture 4Cost, quality and resources

Board summary of the project flow: business case (NABC) → charter → customer requirements → WBS → schedule → network diagram → critical path. For each work package decide: 1 time, 2 number of people, 3 budget, 4 skills of people, 5 risk, 6 quality parameters (CTQ, critical to quality). Requirements come from customer, company, government and the real end user, in categories of performance, quality and cost.

Cost management

  1. Plan cost management: how costs will be estimated, budgeted, managed, monitored and controlled.
  2. Estimate costs: approximate the monetary resources needed; repeated periodically.
  3. Determine budget: aggregate activity or work-package estimates into an authorized cost baseline.
  4. Control costs: monitor status, update costs, manage changes to the baseline.
TypeMeaningExamples
DirectIncurred by the project, tied to specific activities; assignable to one product or serviceWages, raw materials, parts, hardware/software, supplies, shipping, subcontractors, consultants, equipment, project travel
IndirectSupports the project; shared by several products or servicesAdvertising, PM overhead, insurance, depreciation, executive salary, admin, security, office, rent, utilities, legal
FixedDoes not change over the life cycleSet-up, rent, insurance premiums, property tax
VariableChanges with the amount of workHourly wages, materials, fuel

Overhead varies by industry (manufacturing 15–25%, retail 20–30%, construction 10–20%, healthcare 25–40%, hospitality 30–50%, professional services 20–35%, IT 15–25%). At MIT, each federal research dollar is about 70¢ direct and 30¢ indirect; the professor's note: ~30% for the budget that runs all activities.

Estimating techniques

  • Expert judgment: knowledge from similar projects and the industry.
  • Analogous: values from a similar previous project; quick but rough.
  • Parametric: statistical relationship between historical data and variables (cost per m² × m²).
  • Bottom-up: estimate each work package or activity in detail and add up; most accurate.
  • Three-point: cE = (cO + cM + cP) / 3.

Estimates are refined as the project progresses: early accuracy −25% to +75%, later −5% to +10%.

Activity costs: each activity gets direct items (salary, labour, material, license, vendor, travel, rent, utilities) plus percentage indirect items (admin 10%, insurance 5%, marketing 5%, management 20% = 40%). Activity 1.1: 5 + 2 + 2 + 1 = 10 → 10 × 1.4 = 14 (×$1000).

Costs over time and funding

Spreading activity costs over the weeks and adding them up gives the cumulative cost curve, the S-curve, which is the cost baseline (lecture example total $361,200). Money is not received continuously: it comes in steps.

Expenses rise smoothly (S-curve); funding arrives in steps and must always stay above the expense curve. BAC = budget at completion; the gap to the project budget is the management reserve.

Reserves

Contingency reserveManagement reserve
CoversKnown unknowns (identified risks)Unknown unknowns
Calculated asProbability × impactUsually 5–10% of the cost baseline
Controlled byProject managerSenior management
Inside cost baseline?YesNo (inside the project budget)

Examples: 60% × $10,000 = $6,000; five risks, two at $10,000 and three at $11,000 → $53,000.

From activity estimates to the bid price.

Tom's PMP example: membership $139 + course $199 + exam $405 + other $300 = $1,043 project cost; + $500 contingency = $1,543 cost baseline; + $100 management reserve = $1,643 project budget.

Inside the margin: EBITDA − depreciation & amortization = EBIT − interest = EBT − taxes = EAT (net profit).

Quality management

  1. Plan quality: identify quality requirements and standards and how compliance will be shown.
  2. Manage quality: turn the plan into executable quality activities.
  3. Control quality: monitor and record results to ensure outputs are complete, correct and meet expectations.
The later a defect is found, the more it costs. Letting the customer find it in the field is the most expensive.
  • Company: build a culture aware of and committed to quality (Japan).
  • Planning/design: build quality into the design (off-line control: Taguchi robust design).
  • Production: examine and correct the process, not only defects (online control: SPC).
  • Outbound: detect defects before shipping (online control: acceptance sampling).
  • Field: warranty, recalls, lost reputation, rework.
Cost of conformance (spent to avoid failures)Cost of nonconformance (spent because of failures)
Prevention: training, documenting processes, equipment, time to do it right
Appraisal: testing, destructive testing loss, inspections
Internal failure (found by the project): rework, scrap
External failure (found by the customer): liabilities, warranty work, lost business

SIPOC and KPIs

Flowcharts show where quality defects can occur and where to put quality checks. Each SIPOC block gets metrics: supplier quality and delivery; input quality and timeliness; process cycle time, efficiency, yield; output defect rate; customer satisfaction and on-time delivery.

Board example: the Motion Design work package that must keep sound level ≤ 65 dB.

Board chain: requirement “sound ≤ 65 dB” (from the end user) → WBS: Mechatronic Design → work package MD3 Motion Design → SIPOC (input: electric motor; output: sound level) → tests (vibration, sound) → control plan: control parameter, sample size, sampling frequency, control limits.

A KPI is a measurable indicator tied to a target. It must be SMART: specific, measurable, achievable, relevant, time-bound. Table columns: quality criterion · KPI · metric · frequency · target · how · data source (e.g. noise · sound level · dB · every 50 units · ≤ 65 dB · sound test · test lab). Cooking example: ingredients → freshness, shopping → cost, cooking → time, tasting → taste.

Resource management

Resources include time, money and equipment, but here the focus is human resources.

  1. Plan resource management
  2. Estimate activity resources (team and physical: materials, equipment, supplies)
  3. Acquire resources
  4. Develop team
  5. Manage team
  6. Control resources
  • Resource breakdown structure (RBS): personnel (roles, levels), materials (grades), equipment. Consider skills, location, availability and market conditions.
  • Head count: capacity (number of people) follows from the time limit and the capability (skills) needed. 400 person-hours in 80 hours → 5 people.
  • Sustainable head count: keep the core staff level; cover peaks by outsourcing and temporary hires on site or remote.
  • Sourcing 25 people: current staff, new qualified hires, new hires to train, transfers from other projects, short-term staff from service companies, subcontracted tasks.
  • For every task: responsible people, resource, location, plus cost, quality and HR details.

Lecture 5Communication and risks

Communications management

Plan communications management develops an approach and plan for communication based on the information needs of stakeholders and the needs of the project. Then: manage communications (Executing), monitor communications (M&C).

  • Technology: conversations, meetings, documents, databases, social media, websites, chosen by urgency, availability, reliability, ease of use, environment, sensitivity, confidentiality.
  • Models: basic sender/receiver (encode → transmit → decode; concerned with delivery) and interactive (ensures understanding through acknowledgement and feedback).
  • Methods: interactive (real-time, multidirectional), push (sent to specific recipients, no feedback, e.g. a letter), pull (recipients access it themselves, e.g. websites).

Dimensions: written, spoken, gestures, media · internal / external · formal (reports, formal meetings, briefings) / informal (emails, social media, ad hoc talks) · official (annual reports to regulators) / unofficial (relationship building).

Successful communication = an appropriate strategy plus appropriate messages in the right formats. The plan defines collection, creation, dissemination, storage, retrieval, tracking and disposition; iterations improve efficiency.

5Cs of written communication: correct grammar and spelling · concise · clear (aimed at the reader's needs) · coherent logical flow · controlling the flow of words and ideas (graphics, summaries).

Skills: active listening; cultural and personal awareness; managing stakeholder expectations; persuading, motivating, coaching, negotiating, resolving conflict.

Communication requirement analysis: 1 identify stakeholders → 2 their information needs (team: detail; sponsor: summaries) → 3 channels (team: Gantt; sponsor: status reports) → 4 frequency (team: daily; sponsor: monthly) → 5 document the plan. Example plan: team, status updates, fortnightly, face to face; vendors, performance review, monthly, video; executives, high-level report, weekly, email.

Risk management

Risk management includes planning, identification, analysis, response planning, response implementation and monitoring. The objectives are to increase the probability and/or impact of positive risks and decrease those of negative risks.

8.1 Plan→8.2 Identify→8.3 Qualitative→8.4 Quantitative→8.5 Plan responses→8.6 Implement→8.7 Monitor

Professor's notes on the slide: risks come from the chain market needs → contract → customer requirements → WBS → work packages (time, quality, budget, people, skills) → risks in time, people, budget, quality → risk list (R1, R2…), analysed with root cause analysis and failure mode analysis. External sources (technology, social/cultural, legal, environmental, economic) can stop the project and drive the go/no-go decision (implicit). Internal sources may jeopardize results: time, money, quality (explicit).

Two levels of risk

Individual project risksOverall project risk
MeaningThe risks in the project; affect project objectivesThe risk of the project; combination of individual risks and other uncertainty
ManagementExplicit, through the risk processImplicit, through decisions on structure, scope, content, context
Possible effectsDelay or acceleration of milestones; overrun or underspendCancellation or de-scoping; extended benefits

Identifying individual risks (6 steps)

  1. Statement template: “Because of <cause>, <event> could occur during <time window>, which could lead to <impact> with an <effect on a project objective>.”
  2. Basic identification: SWOT, analogy.
  3. Detailed identification: interviews, assumptions analysis, document reviews, Delphi technique, brainstorming.
  4. External cross-check: knowledge from outsiders; checklists, categories.
  5. Internal cross-check: each risk corresponds to an element in the WBS.
  6. Final statement: one statement per risk; flowchart and fishbone diagram to clarify causes and effects.

Identifying overall risk

A higher view is needed: PESTLE (political, economic, social, technological, legal, environmental), PESTLIED (+ international, demographic), STEEPLE (+ ethics), InSPECT, SPECTRUM, TECOP (technical, environmental, commercial, operational, political), VUCA (volatility, uncertainty, complexity, ambiguity).

Risk breakdown structure

Level 0 all sources → 1 technical (scope, requirements, estimates, technology, interfaces) · 2 management (PM, program/portfolio, operations, organization, resourcing, communication) · 3 commercial (contract terms, procurement, suppliers, subcontracts, client stability, partnerships) · 4 external (legislation, exchange rates, site, weather, competition, regulatory). Example: Risk 1.2 may not hire skilled personnel; 2.5 license fee underestimated; 3.4 contract not closed in time; 4.1 supplier delays delivery.

Assessing risks

Two dimensions: uncertainty (probability, frequency, likelihood: low/medium/high) and significance (effect, impact, consequence on time, cost, performance). Scale example: very high = >70%, >6 months, >$5M; very low = 1–10%, 1 week, <$100K.

Two-dimensional probability–impact matrix from the lecture. Numerically, score = probability × impact (probabilities 0.1–0.9; impacts 0.05–0.80), mirrored for threats and opportunities.

Three-dimensional: Risk Priority Number RPN = impact × probability × detectability (each 0–10, total 0–1000). Categories: extremely high 512–1000, high 216–511, medium 64–215, low 8–63, extremely low 0–7. Example: R4.3 = 8 × 9 × 8 = 576, priority 1; R2.4 = 280; R1.1 = 48; R5.1 = 24.

Quantitative: Monte Carlo simulation

Gives better certainty on the probability of outcomes in cost, schedule and performance. Inputs are probability distributions (x1, x2, x3); the model f(x) samples them thousands of times; outputs are a histogram and an S-curve.

Lecture example: three tasks (5, 8, 4 weeks; early finish total 12, late finish total 22). P50 ≈ 16.5 weeks, P90 ≈ 19.5 weeks.

Budget example: the $2.2M target has a 23% chance; expected value $2.35M; 85% chance of $2.45M or less. On the reserve diagram: base cost → project contingency → management reserve; beyond that is risk to the project budget, then risk to the business.

Risk responses

PriorityThreatsOpportunities
HighEscalate: outside scope or beyond PM authority → program/portfolio level
Avoid: eliminate the threat (change scope, schedule), probability → 0
Escalate: same
Exploit: make sure it happens, probability → 100% (most talented resources, new technologies)
MediumTransfer: a third party bears it (insurance, warranties)
Mitigate: reduce probability/impact (less complex processes, more tests, a more stable seller)
Share: a third party shares the benefit (partnerships, teams, joint ventures)
Enhance: increase probability/impact (add resources to finish early)
LowAccept: no proactive actionAccept: no proactive action